惯性聚合 高效追踪和阅读你感兴趣的博客、新闻、科技资讯
阅读原文 在惯性聚合中打开

推荐订阅源

D
DataBreaches.Net
有赞技术团队
有赞技术团队
Jina AI
Jina AI
H
Help Net Security
D
Docker
钛媒体:引领未来商业与生活新知
钛媒体:引领未来商业与生活新知
Blog — PlanetScale
Blog — PlanetScale
Hugging Face - Blog
Hugging Face - Blog
罗磊的独立博客
MyScale Blog
MyScale Blog
N
Netflix TechBlog - Medium
B
Blog RSS Feed
Martin Fowler
Martin Fowler
WordPress大学
WordPress大学
T
The Blog of Author Tim Ferriss
U
Unit 42
Cyber Security Advisories - MS-ISAC
Cyber Security Advisories - MS-ISAC
MongoDB | Blog
MongoDB | Blog
美团技术团队
M
MIT News - Artificial intelligence
阮一峰的网络日志
阮一峰的网络日志
博客园 - 司徒正美
Microsoft Security Blog
Microsoft Security Blog
IT之家
IT之家

Comments for Construction Management

Six reasons local authorities and developers should think timber-first - Construction Management Hackitt slams industry use of outdated design and build contracts - Construction Management Retention of older workers vital for construction productivity  - Construction Management Eurovia Surfacing trials electric asphalt paver on Essex road - Construction Management What if we stopped measuring construction projects by what they build? - Construction Management Free suicide prevention training launched for construction workers - Construction Management ‘Thousands’ mull quitting construction over state of loos on site, survey shows - Construction Management CIOB Academy launches bite-sized courses to tackle skills gap - Construction Management Company and director fined over dangerously botched home extension - Construction Management Construction's biggest AI challenge isn't technology: it's people - Construction Management Blenheim Palace reveals restoration ahead of October completion - Construction Management New research says extra cost of Passivhaus can be as low as 2% - Construction Management Kier prison project puts rehabilitation at heart of social value agenda - Construction Management BAM’s green wall and Mace at City Hall | The best images of July 2026 - Construction Management CIOB Tomorrow’s Leaders representative named APM Student of the Year - Construction Management A view from Amazon on AI and human capability in construction - Construction Management Skills charity to launch workforce competence platform - Construction Management Looking beyond the hard hat: what site life taught me about mental health - Construction Management New construction minister replaces McDonald in reshuffle - Construction Management How can we live in this heat? - Construction Management Empower regions to develop construction skills, CIOB urges Burnham - Construction Management Bricklaying robots from the Netherlands target the UK - Construction Management Subsidising declining apprenticeship numbers just isn’t the answer  - Construction Management Wellbeing: good intentions must turn into meaningful outcomes - Construction Management Employer confidence key to success of construction skills package, says NAO - Construction Management How would a Grenfell Tower replica be used in a criminal trial? - Construction Management Who owns construction knowledge in the age of AI? - Construction Management CITB fund supports employer-led net-zero skills projects - Construction Management ‘Tunnels in eight years’: Shetland council votes to pursue fixed links - Construction Management Risk-based approach agreed for construction apprenticeships reform - Construction Management
‘How do we structure a contract claim?’
Mark Rimmer · 2026-05-05 · via Comments for Construction Management

Our latest Contract Clinic question comes from a contractor facing mounting delays and costs resulting from unforeseen issues on a hotel refurb. Mark Rimmer looks at how to approach a claim

Image: Dreamstime
Image: Dreamstime

The question

We are working on a live project, a refurbishment of a hotel in Lancashire, and a number of unexpected issues have arisen that were not part of the original plan, resulting in delay and additional cost. How do we protect our contractual position and ensure we can recover loss and time under the contract?

The answer

Firstly, the term “claim” is often viewed negatively and is something many people prefer to avoid. However, in construction contracts, a claim simply involves exercising a right provided for under the contract. Once proven, it provides legitimate entitlement, therefore a claim should not be viewed negatively.

Claims can be either informal or formal. An informal claim includes matters such as variations, where the contract usually provides a straightforward mechanism for adjusting the contract sum. In these cases, a formal dispute‑resolution process isn’t normally required.

A formal claim arises when an issue falls outside the usual procedures for adjusting the contract sum, such as a breach of contract or delay event that leads to a financial loss. These matters tend to be more complex to resolve and quite often a formal dispute-resolution process is required.

What are the procedures?

Firstly, and most importantly, you must follow the procedure as described within the contract. This generally includes issuing a notice that details the particulars of the matter and references the relevant clause or clauses. The notice must comply with any specific requirements set out and agreed in the contract. If you get this step wrong, the rest of the claim process may be undermined.

There are four key elements that must be established to demonstrate entitlement to a claim.

  1. The cause. What was the event? This refers to the change or circumstance that gave rise to the loss. This could be employer‑caused delays, variations or changes in legislation. Whatever the situation, there must be a clear link between the cause and the event.
  2. The effect. This must be a direct consequence of the event, and it must result in a demonstrable loss. This is often the most challenging aspect for many project teams, as it requires a clear explanation of how the cause led to the effect and proving a direct, evidence‑based link between the two.
  3. Entitlement. There must be a contractual basis, or an equivalent statutory right, that gives you entitlement to make the claim.
  4. Substantiation. As we all know, records are essential to a successful claim. Ideally, these should be contemporaneous ie created and shared at the time the event occurred to ensure they can be relied upon as credible evidence. Strong, well‑kept records provide a solid base for any claim.

Presenting the claim

Keep it simple. Don’t begin with what you want and then try to justify it. Start with the original plan and set out the sequence of events that led to the claim. Clearly explain the cause and the resulting effect and, whatever you do, avoid trying to sound like a lawyer, there’s no need for overly complex language. Your writing should be concise, clear and to the point.

Here’s how you should structure the claim:

  • Begin with an executive summary that condenses the dispute into no more than a couple of pages.
  • Provide a statement of claim that expands on the summary and sets out the amounts claimed and other key details.
  • Identify and explain the relevant contract terms and particulars that underpin the claim.
  • Present the cause‑and‑effect narrative, clearly setting out the sequence of events and demonstrating how the cause led to the effect and created entitlement.
  • Use appendices for all supporting evidence, including records, analyses, and detailed documentation.

The above should help you put together a strong and well‑structured claim, but don’t hesitate to seek expert support if this isn’t something you handle regularly.

Mark Rimmer is a director at Decipher.