惯性聚合 高效追踪和阅读你感兴趣的博客、新闻、科技资讯
阅读原文 在惯性聚合中打开

推荐订阅源

V
Visual Studio Blog
罗磊的独立博客
宝玉的分享
宝玉的分享
奇客Solidot–传递最新科技情报
奇客Solidot–传递最新科技情报
V
V2EX
酷 壳 – CoolShell
酷 壳 – CoolShell
T
Tailwind CSS Blog
博客园_首页
量子位
月光博客
月光博客
钛媒体:引领未来商业与生活新知
钛媒体:引领未来商业与生活新知
博客园 - 司徒正美
人人都是产品经理
人人都是产品经理
让小产品的独立变现更简单 - ezindie.com
让小产品的独立变现更简单 - ezindie.com
爱范儿
爱范儿
S
SegmentFault 最新的问题
雷峰网
雷峰网
小众软件
小众软件
博客园 - 聂微东
美团技术团队
Apple Machine Learning Research
Apple Machine Learning Research
WordPress大学
WordPress大学
Jina AI
Jina AI
Hugging Face - Blog
Hugging Face - Blog

Construction Management

Government rolls out digital planning tool to all local authorities - Construction Management How designing for repeatability could reshape construction - Construction Management Low-carbon road job: Emissions cut in half with hydrogen and electric gear plus recycled asphalt - Construction Management How new towns offer a chance to revolutionise housing delivery - Construction Management New mental health code aims to stop workplace pressures reaching crisis point - Construction Management CITB backs Scottish prison employment programme - Construction Management Heat on site: is it time for a maximum working temperature? - Construction Management FE students tackle infrastructure projects in Constructionarium pilot - Construction Management Into the deep: Barhale picked for £12.5m tunnel inspection contract for Thames Water - Construction Management Resin injection provides quick fix for Kier’s rotting-tunnel problem - Construction Management Labour shortages are now fuelling construction disputes - Construction Management Companies fined after platform collapse breaks man’s neck - Construction Management Rick Willmott awarded OBE in King’s Birthday Honours List - Construction Management Construction professionals invited to take part in salary survey - Construction Management Estate management leadership must be driven by data Laing O’Rourke: design phase collaboration is key to MMC success HSE prepares guidance for using robots alongside humans Bluebeam extends functions and adds more AI to Max Toasty for £1.19 a day: heat pumps beat boilers in new home tests Companies fined after CCTV captures harrowing fall through skylight Video | BAM uses helicopter to install heat pumps on top of London’s Broadgate Tower Sorry, what’s a data centre? Survey shows 89% of people have no idea Video | Reds10’s ambitious targets for industrialisation Quieter decisions, greater impact: why social value must move from metrics to meaning AI recruitment platform launches to address construction skills shortage CITB launches accelerated apprenticeships Pride in Property 2026 launches with support from major real estate firms Can an assignee adjudicate under the Construction Act? Robertson to restore Grade II Henderson Hall after devastating blaze Shetlanders mull ditching ferries for subsea tunnels between islands
How BAM planned the demolition of Gateshead flyover in 4D...
Ben Thompson · 2026-06-24 · via Construction Management
Aerial shot of Gateshead Flyover. Image: BAM UK & Ireland
Image: BAM UK & Ireland

BAM UK & Ireland and Thompsons of Prudhoe faced a challenge when planning the demolition of the Gateshead Highway flyover. 4D visualisation and planning were key to overcoming the challenge, reveals BAM’s Ben Thompson.

The demolition of the Gateshead flyover represents one of the most complex infrastructure challenges currently being undertaken in the UK. Once carrying more than 40,000 vehicles a day, the 1960s post‑tensioned structure formed a key route into the centre of Gateshead and Newcastle and is now being dismantled under significant technical, logistical and public scrutiny.

The Gateshead flyover was closed in December 2024 following inspections that identified serious concerns with one of its supporting pillars. Subsequent investigations revealed more extensive deterioration, including long-term drainage failures and water ingress within the structure.

BAM UK & Ireland and Thompsons of Prudhoe faced a challenge with planning the demolition of Gateshead Highway flyover
Investigations revealed extensive deterioration, including long-term drainage failures and water ingress within the structure. Image: BAM UK & Ireland

Back to the beginning

While the flyover was a complex feat of engineering when it was built in the 1960s, its demolition presents an even greater challenge. At the time of its construction, there was no requirement to produce detailed demolition plans. As a result, the team returned to the original archive drawings, working from first principles to understand the load paths through the bridge, how it behaves, and how it would respond during progressive dismantling (see image below).

Schematic of Gateshead Flyover showing load paths during dismantling.
Image: BAM UK & Ireland.
Image: BAM UK & Ireland

The scale of the structure, its proximity to surrounding buildings and live roads, and the reliance on extensive temporary works meant that traditional planning outputs alone could not fully communicate the sequence, risk and constraints involved.

From an early stage, the project team recognised the value that a 4D model could offer – not just as a visual output, but as a practical planning tool. The process began with an initial meeting to define how the model would be used and what the project team needed from it. This was crucial in setting expectations and establishing scope, as a 4D model is only as effective as the information that underpins it. At this point, existing data was reviewed, and gaps were identified, highlighting where additional information would need to be developed in-house to accurately represent the proposed methodology.

What was required?

4D visualisation of Gateshead Flyover demolition
Image: BAM UK & Ireland

The information provided to support the model included the construction programme from P6, an existing 3D model of the flyover, a 3D topographical survey, a non-geolocated model of the propping system, and a series of 2D temporary works drawings showing elements such as scaffold, excavator runways and road protection mats.

While this formed a strong foundation, it quickly became clear that additional modelling work would be required to fully capture the complexity of the demolition sequence and the interfaces between permanent works, temporary works, plant and traffic management.

To address this, a significant amount of supporting information was produced in‑house. This included a refined 3D topographical model, which in turn helped the development of a context model produced in Infraworks to provide a wider urban and highway context, and detailed placement of the props along with associated stone pads.

Additional elements, such as parapets, indicative delamination survey zones, and missing parts of the existing model, such as abutments/reinforced earth, were also modelled to ensure the model was as close to the real world as possible.

4D visualisation of Gateshead Flyover demolition
Image: BAM UK & Ireland

Temporary works formed a major component of the model. Protective measures such as protection of one of the footbridges, a scaffold to protect adjacent buildings, protection of the pedestrian subway, and works to partly demolish the Hilda House car park were all modelled explicitly, rather than implied. As mentioned above, stone ‘runways’ and road protection mats also had to be modelled from the 2D temporary works drawing.

Plant was also represented in detail, including excavators with the correct attachments, such as buckets, munchers and debris protection screens. Traffic management was not treated as an afterthought either: road closures and diversion routes were incorporated, so the impact on the surrounding network could be visualised alongside the demolition works.

What was delivered?

Once this modelling work was complete, everything was brought together in Synchro 4D Pro. The model was then carefully structured and linked to the programme, allowing activities to be visualised spatially and temporally. This is where the real value of 4D planning began to emerge. Working closely with the site team, the model was developed and refined over several weeks. Sequences were adjusted, assumptions were tested, and the programme was optimised according to what the model revealed.

The 4D model was used during collaborative planning sessions on site, where it helped to support discussions with subcontractors and the wider delivery team. Being able to see the sequence, access arrangements, and temporary works in context allowed issues to be identified far earlier than they otherwise would have been, reducing risk and improving confidence in the planned approach.

Beyond delivery

Another important step was ensuring the model could be used by the site team beyond pre‑recorded videos. To support this, in-house training was delivered for the Synchro OpenViewer to enable team members to navigate the model themselves. This allowed the 4D model to be used in daily planning conversations, rather than being limited to formal presentations or static exports.

The Gateshead flyover scheme clearly demonstrates the benefits of proper 4D planning when embedded into the project rather than treated as an add‑on. The model improved understanding of complex demolition sequences, helped to identify and manage risk, supported programme optimisation, and significantly enhanced communication across the project team.

Most importantly, it created a shared visual language that allowed engineers, planners, agents and subcontractors to engage with the plan in a meaningful way.

4D visualisation of the demolition of Gateshead Flyover. Image: BAM UK & Ireland
Image: BAM UK & Ireland

By the time demolition began, the value of the 4D model had already been realised through planning, coordination and risk reduction. By integrating programme, temporary works and site constraints into a single visual environment, the team was able to develop a more robust and well-tested demolition strategy ahead of works starting on site.

As the project progresses, the model will continue to play a key role in supporting delivery, with further benefits expected to emerge through its use in tracking progress, refining sequencing, and maintaining alignment between the planned approach and site operations.

Ben Thompson is production specialist (4D) in BAM’s Digital Project Solutions team.